Breakthrough achieved of longest tunnel on Panvel-Karjat suburban rail line

Updated on: 07 June,2024 08:45 PM IST  |  Mumbai
mid-day online correspondent |

The excavation of which began on February 22 last year. Breakthrough of the 2,265 meter long Wavarle tunnel was achieved in the afternoon in the presence of MRVC CMD Subhash Chand Gupta and other senior personnel, said chief public relations officer Sunil Udasi

Breakthrough achieved of longest tunnel on Panvel-Karjat suburban rail line

File Pic

Listen to this article
Breakthrough achieved of longest tunnel on Panvel-Karjat suburban rail line
x
00:00

A successful breakthrough of the longest tunnel on the under-construction Panvel-Karjat suburban railway line has been achieved, reported PTI citing Mumbai Railway Vikas Corporation on Friday.


As per the PTI report, the excavation of which began on February 22 last year. Breakthrough of the 2,265 meter long Wavarle tunnel was achieved in the afternoon in the presence of MRVC CMD Subhash Chand Gupta and other senior personnel, said chief public relations officer Sunil Udasi.


"The successful breakthrough of the tunnel represents a major milestone in the Panvel-Karjat railway project, paving the way for enhanced connectivity and transportation efficiency in the Mumbai suburban region," Udasi said.


The Panvel-Karjat line, being built as part of the Mumbai Urban Transport Project Phase 3, has three tunnels, the other two being 219 metres and 320 metres long, he added.

"The Wavarle tunnel, measuring 7.323 metres in height and 13.282 metres in width, was excavated using the New Austrian Tunnelling Method (NATM). It will be the first ballastless track of the Mumbai suburban network and has features like public refuge areas, a tunnel control system (SCADA), lighting, firefighting and ventilation mechanisms meeting contemporary international standards," Udasi informed.

"Significant challenges were encountered, including fractured rock masses with water seepage and minimal cover during the excavation as well as two water streams crossing the tunnel alignment. Despite these challenges, an average underground excavation output of 175 metres per month was achieved through meticulous planning, with two rounds of blasting per day during the day as night time blasting is not allowed," Udasi pointed out.

In addition to the Panvel-Karjat double line project, which is valued at Rs 476 crore, MRVC has undertaken a number of projects under the MUTP-3 initiative, including the quadrupling of tracks between Virar and Dahanu Road on the Western Railway, the elevated suburban link between Airoli and Kalawa stations on the Central Railway, the procurement of 565 suburban locals, and trespass control on the mid-section on the Central and Western Railway.

Mumbai Railway Vikas Corporation (MRVC) is a joint venture of the Union and Maharashtra governments and is dedicated to improving suburban rail infrastructure to provide commuters enhanced travelling experience, said officials. 

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Register for FREE
to continue reading !

This is not a paywall.
However, your registration helps us understand your preferences better and enables us to provide insightful and credible journalism for all our readers.

Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK